|
|
|
Larger
justice center plan met with shock
By
Scott McLeod
A
work session last week with architects designing Haywood Countys proposed
new justice center revealed just how far apart opinions still are about
the project.
Architects were hopeful the meeting might lead to approval of the schematic
design afor the $4 million parking garage and the $14 million justice center
(that price includes only construction costs). They passed out proposed
construction contract timelines that opened with schematic approval
on Feb. 27.
The only thing agreed to at the meeting, though, was that the building needed
to be smaller and architects should have been told that before coming all
the way from Orlando.
County commissioners — all except Bill Noland — expressed surprise
that architects delivered a proposal that actually enlarged the building.
Commissioners had voted two weeks ago to eliminate two of the seven courtrooms
and reduce the building from four to three stories.
I am astounded to see the size of the building increasing, said
Commissioner Mary Ann Enloe.
Members of the public and county commissioners ended up focusing on the
fact that the county administration had not relayed to architects the desire
for a smaller building. County Manager Jack Horton, however, said the work
session was the place where those changes should be discussed.
Im appalled that the message did not get to (the architects)
that Hawyood County was interested in a smaller design. Did you even get
the message that the people wanted a reduction in size? asked Ron
Bradshaw.
When all commissioners had spoken, there was still wide disagreement over
how the project will proceed, how large the building should be, and what
should be built first — the justice center, the jail or the parking
garage. Commissioner Carlyle Ferguson may have best summed up that confusion.
I dont think the program is going to change a lot, but the difference
between 17,000 square feet and 104,000 square feet is too wide, said
Ferguson.
He was referring to the recommended additional space needed for judicial
services in the Administrative Office of the Courts (17,000 square feet)
and the plan presented by HLM designers (104,000 square feet).
Doug Kleppin and Clay Ransone of HLM Design came to Waynesville with a reworked
schematic. In the new plan, the justice center had five finished courtrooms,
was about 50-feet tall, was 50 feet back from Main Street, and was three
stories — and increased in overall size from 94,000 to 104,000 square
feet.
These are 100-year buildings, and they give you some flexibility as
to how you grow, Kleppin.
The revised plan included about 10,500 squre feet of shell space.
This is non-designated room to allow for growth. Since it is unfinished,
it is cheaper to build. Some of the increase was attributed to eliminating
the fourth floor. That caused the foundation footprint to grow because space
was added on other floors. That substantially increased the square footage
in the basement.
Commissioners, however, were not interested in 100-year plans. County Board
Chairman Jim Stevens said the voters he has spoken with want the county
to build for 20 years.
Its not smart, but thats what people are saying we can
afford now, said Stevens.
The commissioners told the architects to chop 30 feet from the floor plan.
Included on the third floor was a 30-foot shell space for future growth
that could serve as offices or another courtroom. Architects will eliminate
that space from all three floors and the basement, and Kleppin said they
could be back with a new schematic within three weeks.
As debate about the size of the building continued, Hortons handling
of the project was called into question. Enloe accused Hor-ton of writing
in a guest column to The Enterprise Mountaineer that the building, once
reduced, could be built without having to purchase the Clyde Savings Bank
property. Horton denied saying it, but Enloe pressed the matter by presenting
a copy of the article to Horton.
I dont think I ever meant that, said Horton.
Later, as Bradshaw asked who was supposed to tell architects to reduce the
size of the building, Kleppin said the firm had been in contact with Horton
and Assistant County Manager Rick Honeycutt. Enloe said commissioners have
been left out of the loop, but that it was their own fault.
It has been my contention all along that the five people seated at
this table have not been involved as they ought to be in this project,
said Enloe. Ill be the first to admit, though, that the buck
stops with us.
After Enloe and Bradshaws remarks, Stevens stood up for the county
manager.
I think I pretty much know what is happening. Jack (Horton) has been
the one talking to them and I dont appreciate the attacks on Jack,
said Stevens.
Ransone and Kleppin also said that the quare footage increase was due to
design realities and misunderstanding of how to proceed. Kleppin also said
the architectural fees for the project were not based on the size of the
building. HLMs contract for the job is $1.2 million.
Commissioner Wade Francis said after the meeting he was surprised at HLMs
proposal for a larger building.
They certainly did not get anything from us, but they got it from
someone, said Francis. This is a problem for me. If we would
have talked to them they would known we wanted a good bit of square footage
taken off.
Enloe was even more critical of the process.
It is extremely important that the message did not get to the architects,
she said. It all goes to leadership. |
|