| |
<< Back
5/12/03
Heavy
rains reveal flaws in erosion laws
By
Becky Johnson
Rains
last week decimated erosion control measures along the Old Asheville
Highway project in Haywood County, spilling tons of sediment into
Raccoon and Richland creeks.
Afterward, the DOT admitted it wasnt keeping mandated inspection
logs. Other state and environmental officials said state staffing
shortfalls and a lack of training for private contractors make it
nearly impossible to adhere to existing sediment and erosion control
laws.
The $11 million Old Asheville Highway project is a half-mile upstream
from Lake Junaluska and next to a designated trout stream. Last weeks
rains destroyed many of the erosion control measures along the 2.2-mile
road-widening project, and for three days mud and water poured under
silt fences, broke through earthen berms and flowed unchecked through
basins meant to trap sediment.
What you looked at yesterday probably looked like a train wreck.
Our devices were not designed to hold up to that, said Jamie
Wilson, DOT construction engineer, after a day and a half of almost
nonstop rain. Three-quarters of our measures are probably destroyed.
Environmental inspectors with the DOT, as well as state inspectors
with the North Carolina Department of Environment and Natural Resources,
said that erosion controls could not be expected to hold up to such
a heavy rain.
But according to state law, erosion control measures should be designed
to withstand a 10-year flood, or 6.5 inches of rain in 24 hours. The
rainstorms last week did not exceed that level, according to the Mountain
Research Station in Waynesville, which is located one mile from the
project. The station records weather data for the National Weather
Service.
Highway workers do not have a rain gauge on the job site as required
by state law, so DOT inspectors do not know what the actual rainfall
was at their site.
Self-monitoring is the rule
The DOT is responsible for designing, maintaining and inspecting
its own projects for proper sediment and erosion control.
On every project, I have someone designated to keep up with
erosion control. They are supposed to do weekly checks and after
every major storm event, Wilson said, citing state law. However,
the DOT did not document any inspections to erosion control devices
during the two recent days of heavy rainfall, nor did they document
any inspections immediately after the rain.
Ive not gone out and looked yet to see what needs to
be done, said Jim Moore, DOT inspector, Thursday morning (May
8) at 10 a.m., three days after the first half-inch of rain fell
and 24 hours after the last drop of rain fell on the site.
A rain this severe, our measures are not designed for this
type of storm. We didnt anticipate this kind of a storm,
Wilson said Thursday. As soon as it is dry enough and we wont
create more damage, well get back out there and fix it.
Highway workers spent some of Thursday, all day Friday, and Monday
morning repairing erosion control measures along the length of the
project.
Understaffed for oversight
There are three levels of oversight for highway projects. The first
two levels are by the DOT itself. The DOT site inspector who monitors
construction activity and keeps an eye on the contractors is also
in charge of keeping up with erosion measures. The state DOT office
has a team of inspectors that will visit projects to make sure the
on-site inspectors are doing their job.
Its kind of an in-house police, explained David
Harris, an environmental inspector with the DOT in Raleigh.
The third level of oversight comes from the Department of Environment
and Natural Resources, which is charged with monitoring highway
projects for compliance.
It took a DENR inspector 15 months to make his first visit to the
Waynesville highway project. Dennis Owenby, a DENR inspector for
highway projects in Western North Carolina, made his first trip
to the site in March in response to a complaint that mud was washing
into the road. He told the DOT to improve certain sediment control
measures and returned a week later to see the work had been done.
We try to work with them for voluntary compliance, said
Owenby.
Statewide, DENR has not issued a fine or stop work order against
the North Carolina Department of Transportation in more than three
years. DENR has only issued about a dozen notice of violations,
a warning one-step below a fine, to the Department of Transportation
statewide in the past three years.
There have been no stop-work orders and there have been no
fines in three years at least, said Mell Nevils, head of the
DENR erosion control division in Raleigh. The DOT has the
ability to approve its own sediment and erosion control plans. They
do a very good job of inspecting their own projects and shutting
them down.
Owenby is one of two inspectors charged with overseeing road projects
in19 counties.
Nevils said DENR is severely understaffed. DENR has 7,000 to 7,500
erosion projects to monitor statewide and only 32 positions. But,
given the states habit of saving money by not filling vacant
positions, about five positions have been vacant for the past couple
of years. As a result, Nevils has spent a lot of time in the field
doing inspections himself.
Given the number of inspectors and number of sites, the average
visit to a site is once every four months, Nevils said.
That is not adequate oversight, he said of the once-a-year
inspection rate on the Old Asheville Highway project. We do
need more people.
The North Carolina Sediment Control Commission made a recommendation
six years ago that the state hire enough state inspectors to check
every site twice a month.
To do that we needed 130 people. We had 20 at the time,
Nevils said. Now at 32 positions, Nevils still has only a fourth
of the staff he needs to do the job the state has assigned his department.
DOT holds water, though
Nevils said the DOT has improved tremendously in the past decade,
however, and that given the amount of land-disturbing activity
they do, they do a pretty good job.
Roger Watson, a representative of the state Homebuilders Association
on the North Carolina Sediment Board, agreed that the DOT does an
effective job at monitoring their own pollution control measures.
A local environmental group, Haywood Waterways Association, has
scientific data that backs up Watsons opinion. The group has
been taking water samples upstream and downstream of the Old Asheville
Highway project for more than six months.
From a casual observation — and the empirical data has
appeared to support it — the DOT sediment erosion control
measures have worked. Theyve either maintained or reduced
the amount of sediment entering Richland Creek from that area,
said Bill Schaefer, who collects the samples for Haywood Waterways
and takes them to Asheville for analysis. If you stand there
and look at it you say Gee whiz, look at this mess,
but DOTs measures are working.
Of the $11-million project, the DOT will spend about $500,000 on
sediment control, according to DOT estimates. The DOT has already
spent $140,000 on erosion control measures, and the project has
another18 to 24 months before completion. A moderately heavy rain
can cost the DOT $5,500 to repair the erosion control measures.
The largest single erosion control expense is $135,000 to restore
the banks of a 600-foot section of Raccoon Creek. The DOT was required
to do environmental work as mitigation to make up for negative impacts
the highway project will have on the environment elsewhere. Workers
have temporarily moved the creek over while spending two months
creating a new meandering streambed.
Random records
The DOT has failed to keep accurate weekly records of erosion control
checks and maintenance for the Old Asheville Highway project.
Federal law requires all construction projects where one acre or
more is disturbed to document inspections of its erosion measures
weekly and within 24 hours of every rainfall of a half an inch.
Private developers are required to keep these records in a separate
log book.
Jim Moore, site inspector for the widening project, said he has
some notes about sediment measures in his site log book, but does
not make regular documentations.
We just look at it and try to fix it, said Moore.
Granted, our documentation is not up to par, said Rick
Styles, project engineer for the road widening project, when asked
to produce the sediment and erosion documentation since the start
of the project.
Jamie Wilson, construction engineer over Division 14, said site
inspectors are going to start keeping erosion control records in
a separate folder.
Harris, DOT environmental inspector in Raleigh, said while keeping
the log is important, the most important issue is making sure sediment
is not running off the site.
Yes, it is important that those guys are documenting to satisfy
(federal law), but its more important that theyre out
there checking those devices and fixing them to make sure theyre
working, Harris said.
According to Nevils with DENR in Raleigh, Projects can change
on a daily basis. If DOT and DENR inspectors only make it
to sites occasionally, documentation is the only way inspectors
can know how the erosion measures have been holding up the days,
weeks and months prior to their occasional visit.
Harris said weekly notes in a log book still would not prove that
the site inspector was making the checks, however. Owenby, the DENR
inspector, said he did not ask to see documentation of erosion control
checks when he visited the Old Asheville Highway site.
The law requiring weekly documentation of erosion control measures
was amended in March of this year to include all developments of
one acre of more. Previously, the law has applied only to developments
of five acres or more.
Its going to get tighter and tighter. Eventually its
going to get to the point where individual landowners who wanted
to apply fertilizer to their lawn would have to take a soil sample,
Harris said. Its coming in stages.
April showers bring failed measures
Phillip Gibson, a member of the North Carolina Sediment Control
Commission who is the the French Broad Riverkeeper, said the state
has good erosion control laws but does not do a good job enforcing
them.
The law is very clear. You have to keep your dirt on your
property, Gibson said.
Dirt was not staying put anywhere during last weeks rains,
and the Old Asheville Highway project was a visible example of that.
Mud flowed across the highway like liquid plasma, in one case seeping
under a persons trailer and out the other side while the trailers
occupants stood outside in the rain and watched.
To prevent the road from flooding, wire screens and gravel meant
to stop sediment were cut open and pried back, allowing silt-laden
water to flow into inlets unchecked. In another area, a 200-foot-long
earthen berm meant to pool water had a channel cut through it, allowing
mud to flow into the creek branch on the other side of the berm.
Possibly the most silt was lost downstream when a flooded Raccoon
Creek, which had been moved into a temporary channel, blasted under
silt fences and destroyed an earthen barricade to reclaim its old
stream bed. It washed away a 10-foot-wide by 200-foot-long swath
of fill dirt from the old stream bed in the process.
Just downstream from the project, silt clogging Lake Junaluska has
proved a costly nuisance. For two winters, bulldozers have scooped
sediment off the bottom of the drained lake, using $1 million in
state funds and about $300,000 in donations and grants. It is a
seemingly endless task, with the bulldozers scraping away one scoop
of silt at a time and the entire lake bed stretching before them.
When we have a heavy rain like we have in past in days, we
see about 900 truck loads of sediment if we were to turn around
and dig out what had come in, said Joetta Rinehart with Lake
Junaluska Assembly. When this rain comes, you dont know
where its coming from, but the whole lake was red.
Gibson said that while the state has tough laws, developers are
not given the tools they need to comply.
The sediment measures we have today are not designed to filter
sediment, they are designed to slow water down so that large particles
will fall out, Gibson said. A gravel pile in front of a drain
creates a retention area where water pools up, giving sediment a
chance to settle to the bottom before the water flows through.
The sediment law is a performance-based law. The law says
you have to keep your dirt on your property. How you do it is up
to you, Gibson said.
Gibson is pushing the state to allocate money for sediment control
experiments in the mountains to develop better techniques. He also
wants a demonstration site where developers could see the proper
installation of erosion control measures.
The state has funded studies in the Piedmont region and the
coastal region, Gibson said. We need to go through each
measure and find out the applicability of it in the mountain region.
Rick Styles, a project engineer with the DOT in the most western
division, said he couldnt agree more. But the DOT isnt
waiting for a separate state study.
David Harris with the DOT environmental unit hopes to conduct a
sediment control study in the mountain region in the next couple
of years to test erosion control devices the DOT can use when building
in close proximity to a stream. Harris said many of the secondary
roads that need widening have no road shoulder and no buffer between
streams and the road where run-off could be pooled, allowing sediment
to settle out.
We need research dollars for Western North Carolina. The measures
that people are using dont work here, Gibson said. The
other question it begs is whether we should be developing as close
as we are to streams in the mountains.
Harris agreed that building close to streams is tricky, and in the
mountains, roads often follow waterways. When widening a road, proximity
to a stream sometimes makes it very difficult to adhere to erosion
control standards. But not widening the road is not an option, Harris
said, because that would put the environment before peoples
need for new roads.
|
|